🚇 Kabatas-Mahmutbey (M7) Metro Line
The metro line is the first metro project in Türkiye designed on a BIM platform using
5D design technology. All design phases were fully developed within the
BIM environment, enabling an integrated and collaborative workflow throughout the project lifecycle.
Throughout the project, significant gains were achieved in terms of both time and cost efficiency.
Accurate quantity take-offs generated during the design phase helped prevent material losses and unnecessary
expenditures on site, thereby minimizing project risks. A 30 % reduction in cable consumption
was achieved, along with approximately 10 % savings across other MEP components.
As a result of BIM-driven decision-making during the construction phase, the originally planned
construction duration of 18 months was reduced to 8.5 months, representing a substantial improvement in project
delivery performance.
Duration: 2016-2022
Our Design Scope
Our team was responsible for the design of the MEP and fire protection systems for this project [Göztepe and Mahmutbey Stations, LPh 1-9]..
The entire planning phase was coordinated using BIM to ensure seamless coordination with the other disciplines.